Development Projects

Community Development Program (CDP) Phase - I

Executing Agency Schemes Cost Allocation Release Exp. / %age
LGCD (19) 159.515 159.515 159.515 155.354
Highways (18) 211.253 211.253 211.253 205.379
Public Health Engineering (5) 28.2 28.2 28.2 27.204
Total (42 Schemes) 400 400 400 387.936 / -97%

SDGs Achievement Program (SAP) Phase - I

Executing Agency Schemes Cost Allocation Release Exp. / %age
Pak PWD for Roads (7) 95.597 95.597 95.597 95.597
FESCO Construction for Electricity (55) 54.403 54.403 54.403 54.403
Total (62 Schemes) 150 150 150 150 / -100

Sectoral Summary of Provincial ADP 2020 - 21

Executing Agency / Package Cost Exp. up to 30 Jun 2021 Allocation
School Education (19) 73.02 - 76.832
Higher Education (3) 350.322 146.402 70.159
Sports (3) 188.396 110.079 39.434
Health (2) 131.976 81.207 28.651
Water Supply and Sanitation (46) 5,469.63 2,962.73 296.754
LGCD (4) 90 41.962 35.038
Roads (17) 1,968.77 989.578 135.186
Public Buildings (5) 714.086 195.042 135.285
Livestock and Dairy Development (1) 7 4 3
Irrigation (1) 437.04 365 0.5
Total (101 Schemes) 9,430.24 4,896.00 820.839
       
Release Exp. / %age    
76.832 3.45 / -4%    
53.483 51.1 / -96%    
39.434 17.237 / -44%    
28.651 2.1 / -7%    
296.754 248.025 / -84%    
35.038 28.061 / -80%    
135.186 82.669 / -61%    
71.885 49.403 / -69%    
3 1.5 / -50%    
0 0%    
740.263 483.545 / -65%    

SDGs Achievement Program (SAP) Phase - II

Executing Agency / Package Schemes Cost Allocation Release
Pak PWD 4 38.985 38.985 38.985
(Roads)
FESCO Construction 105 119.983 119.983 119.983
(Electricity)
SNGPL 1 31.032 31.032 31.032
(Sui Gas)
Total 110 190 190 190
         
Exp. / %age Remarks      
38.985 Funds Transferred to Pak PWD      
-100% Work in Progress      
119.983 Funds Transferred to FESCO      
-100% Work in Progress      
158.968 Scheme Sent to Federal Government for Approval      
-84%        

Rural Accessibility Program (RAP) Phase - I

 
Scheme PP No. Cost Tehsil
Gojra Pansera Road at Chak No. 279/JB to Adda Naya Lahore Via Chak No. 337/JB PP-118 56.737 Tehsil Gojra District Toba Tek Singh (Length = 5.00 km)
Chak No. 390/JB to Chak No. 395/JB along the Canal PP-121 60.666 Tehsil and District Toba Tek Singh (Length = 6.00 km)
Widening of Road from Kamalia - Chichawatni Road to Syed Mousa Via Mauza Mamber PP-122 59.168 Tehsil Kamalia District Toba Tek Singh (Length = 5.20 km)
Pir Mahal - Sindhilianwali Road to River Ravi Protection Bund Road Chak No. 760/GB PP-123 60.481 Tehsil Pir Mahal District Toba Tek Singh (Length = 5.50 km)
Total   237.052  
       
Release Exp. / %age Remarks  
218.938 52.218 Completed  
  59.403 Completed  
  52.782 Completed  
  54.535 Completed  
218.938 million 218.938 million    

Punjab Municipal Services Program

Local Government Schemes Cost Agreement Cost
Municipal Committee TTS 44 50 47.824
Tehsil Council TTS 32 49.313 47.549
Municipal Committee Kamalia 24 50 49.059
Tehsil Council Kamalia 13 28.283 27.141
Municipal Committee Pir Mahal 37 50 45.451
Tehsil Council Pir Mahal 29 40.197 40.063
Tehsil Council Gojra 23 20.248 20.745
Total 202 288.041 277.832
       
Exp. %age Remarks  
40.756 85% In Progress 02 / Completed 42  
45.909 97% All Schemes Completed  
31.917 65% In Progress 05 / Completed 19  
21.751 80% All Schemes Completed  
33.931 75% In Progress 02 / Completed 35  
38.275 96% In Progress 01 / Completed 28  
18.413 89% In Progress 02 / Completed 21  
230.952 83% In Progress 12 / Completed 190  

Sugarcane Development Cess Program

 
Tehsil Scheme Cost Allocation
 
Gojra District Toba Tek Singh Naya Lahore to Chak No. 340/JB via Chak No. 339/JB (Kajlay) 9.648 6.915  
District Toba Tek Singh 0.53KM Toba Shorkot Road Al-Hilal Chowk to Shabhbaz Chowk (Left Side) 10.524 8.998  
  Widening/Improvement Sindhilianwali to Wagi (Sindhilianwali) Kamalia Road from km no. 0.50 to km no. 0.96), L = 0.46 km 9.422 7.29  
  57/4 Tukra to Chak Sher Singh 7.824 5.653  
  Rehabilitation/Widening of Road from Token Post to Inayat Shah Pir Mahal Road, L = 2.98 km 16.664 12.061  
Total   54.082 40.917  
         
Exp. / %age Remarks      
0.264 / -4% Dismantling Road Edging is in Progress, Earth Work for Berms in Progress      
4.587 / -51% Scarifying Completed, Sub Base = 0.40 km, Rigid Pavement = 0.30 km      
0.264 / -4% Earth work in Progress, Dismantling of Road Edging in Progress      
0.264 / -5% Earth Work = 0.20 km      
0/0% Converts in Progress      
5.379 / -13% Work Allotted to the Contractor      

Note: All amounts (costs) are in PKR Million.